Revolution Update

We have a Treadmill, a Shoulder Press, a Spin Bike and one of 2 different types of Cross Trainer set up in reception. The rest of the equipment arrives between Christmas and the New Year. Please feel free to ask questions and have a go on the kit.

Although the majority of the building works will take place over the Christmas shutdown, we have started other works already, namely:

  • Rebalanced the ventilation and air con in studio 2 and 1
  • New lighting in the Gym and mezzanine floor
  • Repairs to male and female shower areas.

Still to do over the shutdown are:

  • New flooring in the gym, studio 2, free weights, stairs and mezzanine floor
  • Redecorate throughout the building including carpeting in reception and corridors
  • Redecorate throughout the male and female changing rooms
  • Removal of TV wall in gym and replacement with a much lower longer affair (all the CV equipment now has built in 15’ TVs with iPod connectivity)

We will try to keep the shutdown period as short as possible. As soon as we have definite dates we will let you know, but current best "guesstimate" is 19th December to 3rd Jan. That only gives us 2 weeks to do an awful lot of work and we are looking at ways in which we can remain partially open. We will keep you posted.

Equipment in Reception

Fix your Membership Prices for 2010 and Beyond

Due to the popularity of our October offers, we have decided to extend our membership deals.

For those of you who have been with us a while, you will have accumulated Loyalty Points which we issued to commemorate our 10 year anniversary (£10 for each full calendar year of membership). This is the last time that you will able to set them off against membership which makes the following deals even cheaper.

November/December Membership Offers:

  • 200 annual memberships at £396 each
  • 100 2 year memberships at £720 each; can be shared between 2 people with one year each
  • 50 3 year memberships at £972; can be shared between 2 people with 1.5 years each
  • 25 10 year memberships at £1998; can be shared between 2 people with 5 years each

To reserve one of these deals, follow the appropriate link below.

Your Membership from January 2010

Our 10 year anniversary comes to an end this December. Unfortunately we can’t keep our prices as low as they have been, and we will have to put them back to a more realistic level. For some of you, this will mean no change; for others it may mean a small increase. To find out more, answer the following questions:

  • Are you of state pensionable age? If yes click here
  • Are you a student in full time education? If yes click here
  • Do you work for: -
    • Any company on Milton Park
    • Any company on Southmead Industrial Park
    • Any company on Harwell campus
    • Any company on Culham campus
    • Emergency services including the Police
    • NHS
    • Oxford County Council
    • If yes click here
  • If you don’t fit into any of the above click here

Schedule of Works

We are making every effort to keep you bang up to date with The Club refurbishment So here is the most detailed schedule of works we have so far worked out with our contractors. We are making every effort to keep as much of the club open as possible during the works as this is something we know you are really keen for us to do.

Area Closure Dates Details Targeted Reopening
Spinning Studio 30.11.09 RPM in Sports Hall 07.12.09
Swimming Pool ALL WORKS IN THIS AREA WILL BE OUT OF HOURS AND WILL NOT AFFECT OUR CUSTOMERS
Studio 1 ALL WORKS IN THIS AREA WILL BE OUT OF HOURS AND WILL NOT AFFECT OUR CUSTOMERS
Reception Area ALL WORKS IN THIS AREA WILL BE OUT OF HOURS AND WILL NOT AFFECT OUR CUSTOMERS
Main Gymnasium 18.12.09 Targeted reopening 3.01.10
Mezzanine Area 08.12.09 Targeted reopening 15.12.09
Ladies Changing Room 28.11.09 Ladies will now be changing in the men’s changing rooms 10.12.09
Men's Changing Room 28.11.09 Men will now be changing in the swimming pool area 04.01.09